*January - December 2026
| |
|
|
|
|
|
Total Permit Fees Collected | $25.00 | $10.00 | $ | $ | $ | $ |
Single Family Dwellings Permitted | *145 | *177 | * | * | * |
|
Estimated Cost of Construction | $75,325,601 | $87,902,979 | $ | $ | $ | $ |
Commercial Buildings Permitted | 3 | 6 |
|
|
|
|
Commercial Estimated Cost of Construction | $6,707,850 | $5,215,673 | $ | $ | $ | $ |
| | | | | | | |
* January 117 SFD (6) Two Family 12 units + (1) Three and Four Family 4 units + (2) Five and More Family 12 units = 145
* February 140 SFD (1) Two Family 2 units + (1) Three and Four Family 4 units + (5) Five and More Family 31 units = 177
July - December 2026
|
|
|
|
|
|
|
Total Permit Fee Collected | $ | $ | $ | $ | $ | $ |
Single Family Dwellings Permitted |
|
|
|
|
|
|
Estimated Cost of Construction | $ | $ | $ | $ | $ | $ |
Commercial Buildings Permitted |
|
|
|
|
|
|
Commercial Estimated Cost of Construction | $ | $ |
| $ | $ | $ |